References

Pre-FEED study of a PGM refinery

The customer planned to build a state-of-the-art PGM refinery to process a metal-rich concentrate. The aim was to achieve an outstanding precious metal yield with maximum product purity in a single step. At the same time, environmental requirements were to be taken into account and energy consumption reduced to a minimum.

Engineering Dobersek developed a fully structurable system concept in the pre-FEED scope.

Commissioning: 2023

Project details
  • Client: Confidential
  • Location: Arab Gulf States
  • Contract type/services: Engineering within the scope of Pre-FEED (Front-End Engineering Design)
Our solution

Engineering Dobersek developed a fully structurable system concept in the pre-FEED scope, which comprises the following main modules:

  • Refinery plant with reactors, melting furnaces and casting equipment
  • Chlorine evaporation system for the preparation of chlorine reagents
  • Waste water treatment plant to meet the strictest environmental standards
  • Analytical laboratory for inline quality control
  • Reagent and auxiliary supply including storage and distribution system
  • Electrical and distribution technology including substation and Pape Rack

By using proven, field-proven system components from leading European OEMs, the concept ensures high operational reliability and easy maintenance. A modular design enables flexible expansions and minimizes investment and installation costs.

Customer benefits

Outstanding product quality: Precise process control guarantees first-class precious metal yield and purity in a single pass.

Maximum availability: 80-110 % of nominal capacity ensures economical production.

Environmentally friendly: State-of-the-art waste water treatment and optimized energy management reduce emissions and operating costs.

Ease of use: Intuitive control system and low-maintenance components extend operating cycles and minimize downtimes.

Cost efficiency: Optimized system structure and modular planning reduce CAPEX and OPEX.

Technical data
  • Feedstock: Feedstock containing PGM concentrate
  • Annual capacity: up to 100 tons of PGM (Au, Ag, Pd, Pt, Rh, Ir, Ru)
  • System availability: 80-110 % of nominal capacity
  • End products:
    • Gold & silver as bars
    • Platinum & palladium as bars and powder
    • Rhodium, iridium & ruthenium as powder
Project highlights
  • Globally unique, environmentally friendly PGM refinery technology
  • Use of field-proven equipment from renowned European OEMs
  • Scalable solution for future capacity expansions

With this pre-FEED study, Engineering Dobersek is once again setting standards in sustainable metallurgy and providing a future-proof basis for ecologically and economically superior PGM processing.

Success stories that count.